Project Update: Rise of the Machines

Project Update: Rise of the Machines

With erection of the main buildings and steel structures continuing to schedule, there has been increased activity as the process equipment is installed. At the heart of the energy from waste plant is the combustion grate which is now in place, and preparations are in hand for the installation of the boiler panels which will capture the energy created from the combustion process and raise steam to drive the turbine and electricity generator.
 

Read More

Project Update: Heavy Metal

Project Update: Heavy Metal

The autumn has seen continued concreting works, with the construction of the turbine hall by continuous concrete pouring (slip forming), as well as the formation of the retaining walls for the building that will house the incinerator bottom ash processing. The last section of concrete floor in the area of the combustion grate and boiler has now been completed, with foundation works for the electricity substation and transformer near completion.

Read More

Project Update: Moving Ever Upwards

Project Update: Moving Ever Upwards

While below ground concrete works continued during the summer months, September saw the buildings start to emerge above ground, with the concrete bunker walls appearing almost overnight. The first elements of the steel frame construction - the supports for the turbine hall – have now been erected, which signals the start of the main process plant installation, and construction of the administration block/visitor centre.

Read More

Project Update Bulletin 7

The project update bulletin provides the latest progress on the construction of Gloucestershire’s Energy from Waste facility.

We have planned a further phase of foundation piling as part of the construction works, which will be commencing this week and continuing, intermittently until mid-June 2-17. This work will mainly be focussed on the bunker area of the site.

Read More

Project Update Bulletin 6

The project update bulletin provides the latest progress on the construction of Gloucestershire’s Energy from Waste facility.

In recent weeks, activities have been focussed on the construction of the capping beams and foundation pads for the main boiler house, and prefabricating steel reinforcements for the Incinerator Bottom Ash (IBA) treatment hall at the eastern end of the building complex.

Read More

Progress Update: Work below ground nears completion

Progress Update: Work below ground nears completion

As of 1st April, we’ve almost completed our work below ground to prepare the site’s foundations. The first phase of foundation piling and excavation is ongoing, as the boiler house is excavated and the waste storage bunker groundwork continues to take shape. All of the concrete works, including the capping beams which sit above the piles, will offer support and strength for the main process plant and buildings of the Facility once complete.

Read More