Project Update Bulletin 18

During September, a special type of protective metal-welded cladding was fitted to parts of the inside of the boiler to prevent erosion by the flue gases during operation. The next stage is to install a refractory lining to the hottest parts of the boiler to protect the furnace shell, in the lower part of the boiler where the waste is incinerated, from the high temperatures it will endure.

Read More

Project Update Bulletin 17

Over summer, we successfully completed the boiler pressure test on schedule. This demonstrated the build integrity of the boiler, and allows follow-on activities to take place, such as installation of the cladding welds inside the boiler, refractory lining which acts as an internal insulation layer, and external insulation. We also successfully carried out the fire water tank integrity test.

Read More

Project Update: Structures Taking Form

Project Update: Structures Taking Form

Over summer, we successfully completed the boiler pressure test on schedule. This demonstrated the build integrity of the boiler, and allows follow-on activities to take place, such as installation of the cladding welds inside the boiler, refractory lining which acts as an internal insulation layer, and external insulation. We also successfully carried out the fire water tank integrity test.

Read More

Project Update: Rise of the Machines

Project Update: Rise of the Machines

With erection of the main buildings and steel structures continuing to schedule, there has been increased activity as the process equipment is installed. At the heart of the energy from waste plant is the combustion grate which is now in place, and preparations are in hand for the installation of the boiler panels which will capture the energy created from the combustion process and raise steam to drive the turbine and electricity generator.
 

Read More

Project Update: Heavy Metal

Project Update: Heavy Metal

The autumn has seen continued concreting works, with the construction of the turbine hall by continuous concrete pouring (slip forming), as well as the formation of the retaining walls for the building that will house the incinerator bottom ash processing. The last section of concrete floor in the area of the combustion grate and boiler has now been completed, with foundation works for the electricity substation and transformer near completion.

Read More

Project Update: Moving Ever Upwards

Project Update: Moving Ever Upwards

While below ground concrete works continued during the summer months, September saw the buildings start to emerge above ground, with the concrete bunker walls appearing almost overnight. The first elements of the steel frame construction - the supports for the turbine hall – have now been erected, which signals the start of the main process plant installation, and construction of the administration block/visitor centre.

Read More